Unmeasured performance is performance on paper only

Bollard pull tests for tugs and speed, manoeuvring and machinery trials for vessels. We set up the test, run the measurement and coordinate class and owner attendance.

Test types
Bollard pull · Sea trials
Attendance
Class · Owner · Surveyor
Output
Measurement report

01Bollard pull test

What a tug can actually pull

Bollard pull is the static pulling force a tug can apply while stationary, and it is the tug’s commercial identity. Contracts, escort requirements and insurance assessments all rest on that figure.

For the test to stand up, the set-up must be right: sufficient water depth, current and wind within limits, towline length to standard, and a calibrated load cell. If any of these is missing, the measurement produces a number but not a certificate.

We organise the test site, the mooring arrangement, calibrated measurement equipment, recording and the attendance of the class surveyor. The output is a measurement report documented together with the date and the conditions.

Bow of a loaded container vessel seen from the quay

02Test conditions

What makes a bollard pull test valid

A measurement taken without the following does not become a certificate.

Water depth
In shallow water propeller efficiency drops and the reading misrepresents reality; the site is chosen with adequate depth.
Wind and current
Wind and current must stay below limits, otherwise external forces contaminate the reading.
Towline length
The distance to the fixed point must be long enough to prevent propeller wash reflection.
Calibrated measurement
A load cell and recorder with valid calibration certificates are used.
Duration and recording
Recording is continuous over a set period; the steady-state value is taken, not an instantaneous peak.
Surveyor attendance
The certificate is issued under the attendance of a class society or independent surveyor.

03Sea trials

Verification after newbuilding and repair

A sea trial is the voyage where it is measured whether the vessel actually delivers the performance promised in the contract. It is run before newbuilding delivery and after major machinery repairs.

Scope varies with the job: speed trial, turning circle, zigzag manoeuvre, crash-stop, anchor trial, steering and machinery load tests, vibration and noise measurement.

Our role is to organise the voyage — area and time planning, an escort tug where required, the measurement team, attendance of class and owner representatives, and reporting of the result.

Harbour and breakwater, wide aerial view

04Trial scope

Test items we run

SPD

Speed trial

Recording the speed–power relationship at several revolutions over a measured distance.

TRN

Turning circle

Measuring advance, transfer and tactical diameter at hard-over helm both ways.

ZIG

Zigzag manoeuvre

Determining the vessel’s response time to helm and its directional stability.

STP

Crash-stop

Measuring stopping distance and time from full ahead to full astern.

ANC

Anchor trial

Verifying windlass capacity and the times for paying out and heaving the cable.

MCH

Machinery load test

Running and monitoring main engine and generators at defined load steps.

A test is worth what its conditions record

The conditions matter as much as the figure itself: depth, weather, draft, displacement and date. When a dispute arises later, it is these records that speak.

Next step

Tell us about the operation and we will work out the right tug and plan with you.